The proposed Jaipur-Pachpadra greenfield expressway would run roughly 350 to 400 km from Jaipur through Kishangarh, Pali and Jodhpur to Pachpadra in Balotra district, at an estimated cost of ₹11,492 crore. Reports place it at the Detailed Project Report (DPR) and land acquisition stage under the National Highways Authority of India (NHAI). No opening date has been announced.
For buyers and landowners the useful question is how much of the route is actually fixed. The answer so far is not much: the corridor is approved in principle, but village-level alignment is still being settled through official notices.
The project at a glance
|
Item |
What the sources say |
|
Length |
About 350 km in the state’s early plan; 350 to 400 km in later reports |
|
Estimated cost |
About ₹11,492 crore |
|
Route |
Jaipur, Kishangarh (Ajmer), Pali, Jodhpur, Pachpadra (Balotra) |
|
Agency |
NHAI, after the project was moved from the state government |
|
Stage |
DPR being prepared; land acquisition under way |
|
Opening date |
None announced |
The length differs between sources because the alignment has not been finalised.
Route and connections
The expressway starts near Jaipur and heads west through the Ajmer, Pali and Jodhpur belt before ending at Pachpadra, where the HPCL Rajasthan refinery complex is located. Patrika reports that it would connect with the planned Beawar-Bharatpur greenfield expressway near Bagru, and that the route is expected to link western Rajasthan with the proposed Delhi-Mumbai Industrial Corridor segment and the Amritsar-Jamnagar expressway.
Rajasthan had earlier listed Jaipur-Jodhpur-Pachpadra, at about 350 km, among nine greenfield expressways it planned. Jaipur-Pachpadra and Bikaner-Kotputli were later handed to NHAI, according to Patrika.
Where the project stands
- Early 2025: the state lists the corridor among nine planned greenfield expressways, with DPR work under way.
- Late 2025: Chief Minister Bhajanlal Sharma directs NHAI to start land acquisition, Patrika reports.
- 17 December 2025: the Ministry of Road Transport and Highways issues a Section 3A notice for land in Pachpadra tehsil, Balotra, under a corridor name that appears connected to this route (explained below).
- Early 2026: Patrika reports the project has Central approval, with land acquisition under way and the DPR being prepared.
The dates for the Patrika reports are approximate, read from the articles’ age.
What the Pachpadra land notice says
Notification S.O. 5864(E), dated 17 December 2025, was issued under Section 3A(1) of the National Highways Act, 1956. It covers about 210.11 hectares, roughly 519 acres, in villages including Kitnod, Bamani, Asotara and Gograd Nadi in Pachpadra tehsil, between Km 269.800 and Km 278.935. The notice names the project as the Jaipur-Kishangarh-Ajmer-Jodhpur Interchange with the Amritsar-Jamnagar Corridor.
AquireAcres could not confirm that this notice covers the western end of the Jaipur-Pachpadra expressway. The project name differs, and a chainage of Km 270 in Pachpadra tehsil does not fit a route that starts at Jaipur, so the notice may use a different chainage basis or relate to a connected corridor.
A Section 3A notice is only the first step. It does not transfer ownership. Anyone interested in the land can object in writing to the competent authority, here the Sub-Divisional Magistrate, Balotra, within 21 days of publication. The authority decides objections by a reasoned order, and compensation is fixed at later stages.
What buyers near the route should check
These are general checks, not findings about any specific plot.
- Look for a notice, not a rumour. Land is formally on an alignment only when it appears in a Gazette notification with survey numbers. Ask for the notice number, and check the Gazette.
- Check which stage the notice is at. A Section 3A notice means acquisition is proposed. Land bought after a notice may still be acquired.
- Do not pay a premium on talk of the expressway. The corridor length, route and timeline are still moving.
- Verify the plot and the project. For plotted layouts, check Rajasthan RERA registration, land conversion and title before paying.
What is not yet known
The sources do not give a final alignment, a construction start date, a completion date, the number of lanes or design speed, or the package-wise contractors. Pages that quote speeds of 100 to 120 kmph, a four-hour Jaipur-Jodhpur drive, a Hybrid Annuity Model or a 2030 opening were not backed by an official document in the material reviewed.